HORIZON-CL5-2024-D3-01-13
DC and AC/DC hybrid transmission and distribution systems -
Call text (as on F&T portal)
View on F&T portalExpected Outcome:
Project results are expected to contribute to all the following outcomes:
- Demonstrated top-down electricity system orchestration of future pan-European AC / DC hybrid system architecture - including offshore grid and energy islands - at different voltage levels (HVDC, MVDC, LVDC) down to DC microgrids.
- Developed methodologies for operational planning and design of DC and AC / DC hybrid systems, considering all possible sources, loads and storage, from high-voltage transmission level to distribution-connected assets. This includes a cost benefit analysis for stability management options.
- Developed methodologies and requirements for interoperability among Multi Terminal, Multi-Vendor MVDC and LVDC systems.
- Demonstrated technologies to be applied to the energy system to address the gradual loss of inertia caused by the increasing penetration of Power Electronics Interfaced Generators (i.e., RES such as PV, Wind, etc.).
- Demonstrated DC transmission and distribution systems and technologies.
- Components and systems for smart substations.
- Close collaboration among the key grid stakeholders (non-exhaustive list: software developers, system manufacturers, TSOs, third-party system integrators, wind turbine manufacturers, offshore wind farm developers, PV plants, storage systems, etc.).
Scope:
Projects are expected to implement the activities in (1) and the practical demonstration in (2) as described below:
A) DC – AC / DC hybrid system Design & Planning
a. Demonstration of software tools for transnational AC/DC hybrid power system planning and management to enable HVAC/HVDC/MVDC/LVDC hybrid systems, such as:
- integration of multi-terminal HVDC systems, both offshore and onshore and HVDC links embedded within the HVAC network as well as HVDC ties (inter-) connecting different control zones and synchronous areas (in full or in back-to-back schemes);
- representation and modelling of transmission and distribution grids as well as multi-energy vector integration (sector coupling) for long-term and for transient and dynamic analysis.
b. Demonstration of reliability and resilience methodologies to address security and adequacy issues and criteria via not only deterministic but also probabilistic (e.g., Monte-Carlo) methods.
c. Demonstration of developed methodologies and requirements for interoperability among Multi Terminal, Multi-Vendor MVDC and LVDC systems.
B) AC and DC Grid Forming Capability
- Functional requirements and demonstration of grid forming capability for hybrid HV AC/DC networks (e.g., offshore wind, HVDC transmission or multi-terminal HVDC grid, potentially associated with energy storage systems).
- Functional requirements and demonstration of grid forming capability for hybrid MV and LV AC/DC networks (grid connected and islanded operation with distributed energy sources).
- Functional requirements and validation procedure for testing grid-forming capabilities offered by HVDC, MVDC and LVDC systems.
C) DC Distribution & microgrids
- Modelling (steady state and transient models) for systems including different typology of RES, EVs, storage and loads (system architecture, voltage level, control, stability, protection, and storage integration).
- Planning and design of MVDC distribution grids as the intermediate layer between the HVDC and the AC or DC Low Voltage local distribution grid and loads.
- Functional requirements for the AC-DC converters, DC-DC converters, switchgear (including protection equipment) and cables based on the different typologies and power rating applications
2. Demonstration, test and validation of the activities developed in (1) in at least three pilots – one for each sub-topic (A, B and C) – in different EU Member States/Associated Countries.
International cooperation with countries of the Mediterranean Region is encouraged.
null
Activities are expected to achieve TRL 4-5 by the end of the project – see General Annex B.
News flashes
Call update: EVALUATION results
Published: 12/09/2023
Deadline: 16/01/2024
Available budget: EUR 246.000.000
The results of the evaluation for each topic are as follows:
D3-01-01
D3-01-02
D3-01-03
D3-01-04
D3-01-05
D3-01-06
D3-01-07
D3-01-08
D3-01-09
D3-01-10
D3-01-11
D3-01-12
D3-01-13
D3-01-14
D3-01-15
D3-01-16
D3-01-17
Number of proposals submitted (including proposals transferred from or to other calls)
12
14
13
13
13
12
14
13
2
101
8
19
5
7
10
6
2
Number of inadmissible proposals
1
Number of ineligible proposals
1
2
1
1
6
Number of above-threshold proposals
7
10
4
6
2
6
8
4
1
26
5
15
3
5
6
3
2
Total budget requested for above-threshold proposals (EUR/millions)
81.9
29.4
35.5
23.6
7.6
18.0
31.5
74.7
10.0
77.7
26.6
75.3
17.9
20.2
32.4
24.5
11.9
Number of proposals retained for funding
2
2
2
2
2
3
2
2
1
9
3
2
2
3
3
1
2
Number of proposals in the reserve list
2
2
2
2
0
2
2
2
0
10
2
2
1
2
2
2
0
Funding threshold
13.5
14.0
13.5
14.0
11.0
13.5
13.0
13.0
10.5
13.5
11.5
13.5
14.0
11.0
13.5
13.5
11.0
Ranking distribution for proposals above the evaluation thresholds
Number of proposals with scores lower or equal to 15 and higher or equal to 14
1
2
1
3
0
2
1
0
0
5
1
1
2
0
1
0
0
Number of proposals with scores lower than 14 and higher or equal to 13
2
1
3
3
1
2
1
3
0
10
1
4
0
1
3
1
0
Number of proposals with scores lower than 13 and higher or equal to 10
4
7
0
0
1
2
6
1
1
11
3
10
1
4
2
2
2
Summary of observer report:
"As independent Observer I was able to acquire deep insight into the call and evaluation documentation and accompanying instructions. I took part in a significant fraction of all briefings and panel meetings, had full access to the online evaluation SEP system and could both monitor the evaluation progress as well as having insight in individual evaluation and consensus reports.
I observed a professionally orchestrated, fair, impartial, expertise-driven, and transparent evaluation exercise. The consensus reports, the ultimate outcome, meet high standards and adhere to the guidelines outlined in the guiding documents and applicable rules.
All consensus panels were managed as equitably as possible, with effective quality control measures, inter-panel collaboration, and comprehensive final cross-checks ensuring a consistent evaluation outcome. The core principles of impartiality, fairness, and confidentiality were followed throughout the full evaluation process."
We recently informed the applicants about the evaluation results for their proposals.
For questions, please contact the Research Enquiry Service.
Call update: EVALUATION results
Published: 12/09/2023
Deadline: 16/01/2024
Available budget: EUR 246.000.000
The results of the evaluation for each topic are as follows:
D3-01-01
D3-01-02
D3-01-03
D3-01-04
D3-01-05
D3-01-06
D3-01-07
D3-01-08
D3-01-09
D3-01-10
D3-01-11
D3-01-12
D3-01-13
D3-01-14
D3-01-15
D3-01-16
D3-01-17
Number of proposals submitted (including proposals transferred from or to other calls)
12
14
13
13
13
12
14
13
2
101
8
19
5
7
10
6
2
Number of inadmissible proposals
1
Number of ineligible proposals
1
2
1
1
6
Number of above-threshold proposals
7
10
4
6
2
6
8
4
1
26
5
15
3
5
6
3
2
Total budget requested for above-threshold proposals (EUR/millions)
81.9
29.4
35.5
23.6
7.6
18.0
31.5
74.7
10.0
77.7
26.6
75.3
17.9
20.2
32.4
24.5
11.9
Number of proposals retained for funding
2
2
2
2
2
3
2
2
1
9
3
2
2
3
3
1
2
Number of proposals in the reserve list
2
2
2
2
0
2
2
2
0
10
2
2
1
2
2
2
0
Funding threshold
13.5
14.0
13.5
14.0
11.0
13.5
13.0
13.0
10.5
13.5
11.5
13.5
14.0
11.0
13.5
13.5
11.0
Ranking distribution for proposals above the evaluation thresholds
Number of proposals with scores lower or equal to 15 and higher or equal to 14
1
2
1
3
0
2
1
0
0
5
1
1
2
0
1
0
0
Number of proposals with scores lower than 14 and higher or equal to 13
2
1
3
3
1
2
1
3
0
10
1
4
0
1
3
1
0
Number of proposals with scores lower than 13 and higher or equal to 10
4
7
0
0
1
2
6
1
1
11
3
10
1
4
2
2
2
Summary of observer report:
"As independent Observer I was able to acquire deep insight into the call and evaluation documentation and accompanying instructions. I took part in a significant fraction of all briefings and panel meetings, had full access to the online evaluation SEP system and could both monitor the evaluation progress as well as having insight in individual evaluation and consensus reports.
I observed a professionally orchestrated, fair, impartial, expertise-driven, and transparent evaluation exercise. The consensus reports, the ultimate outcome, meet high standards and adhere to the guidelines outlined in the guiding documents and applicable rules.
All consensus panels were managed as equitably as possible, with effective quality control measures, inter-panel collaboration, and comprehensive final cross-checks ensuring a consistent evaluation outcome. The core principles of impartiality, fairness, and confidentiality were followed throughout the full evaluation process."
We recently informed the applicants about the evaluation results for their proposals.
For questions, please contact the Research Enquiry Service.
Opening date: 2023-09-12 (3 years ago)
Closing date: 2024-01-16 (2 years ago)
Procedure: single-stage
Budget: 13,000,000
Expected grants: 2
Contribution: 6,000,000 - 6,000,000
This call topic has been appended 6 times by the EC with news.
-
2024-05-15
call update: evaluation resultspublished... -
2024-05-15
call update: evaluation resultspublished... -
2024-01-17
the call for proposals horizon-cl5-2024-... -
2024-01-17
the call for proposals horizon-cl5-2024-... -
2023-09-12
the submission session is now available... -
2023-09-12
the submission session is now available...
HORIZON-CL5-2024-D3-01
Call topics are often grouped together in a call. Sometimes this is for a thematic reason, but often it is also for practical reasons.
There are 16 other topics in this call:
- HORIZON-CL5-2024-D3-01-01
- HORIZON-CL5-2024-D3-01-02
- HORIZON-CL5-2024-D3-01-03
- HORIZON-CL5-2024-D3-01-04
- HORIZON-CL5-2024-D3-01-05
- HORIZON-CL5-2024-D3-01-06
- HORIZON-CL5-2024-D3-01-07
- HORIZON-CL5-2024-D3-01-08
- HORIZON-CL5-2024-D3-01-09
- HORIZON-CL5-2024-D3-01-10
- HORIZON-CL5-2024-D3-01-11
- HORIZON-CL5-2024-D3-01-12
- HORIZON-CL5-2024-D3-01-14
- HORIZON-CL5-2024-D3-01-15
- HORIZON-CL5-2024-D3-01-16
- HORIZON-CL5-2024-D3-01-17
Showing the latest information. Found 196 versions of this call topic in the F&T portal.
Information from
- 2026-10-08_08-05-13
- 2026-10-08_08-04-16
- 2026-10-07_08-00-19
- 2026-10-07_07-59-48
- 2026-10-06_08-03-16
- 2026-10-06_08-02-28
- 2026-10-05_07-59-42
- 2026-10-05_07-59-06
- 2026-10-04_08-00-48
- 2026-10-04_08-00-03
- 2026-10-03_07-59-11
- 2026-10-03_07-58-30
- 2026-10-02_08-01-34
- 2026-10-02_08-00-11
- 2026-10-01_08-03-22
- 2026-10-01_08-01-45
- 2026-09-29_08-30-39
- 2026-09-29_08-28-12
- 2026-09-28_08-30-18
- 2026-09-28_08-27-48
- 2026-09-27_08-28-37
- 2026-09-27_08-26-05
- 2026-09-26_08-26-04
- 2026-09-26_08-23-35
- 2026-09-25_08-27-39
- 2026-09-25_08-25-14
- 2026-09-24_08-27-55
- 2026-09-24_08-25-48
- 2026-09-23_08-25-47
- 2026-09-23_08-23-13
- 2026-09-22_08-25-31
- 2026-09-22_08-23-10
- 2026-09-21_08-21-22
- 2026-09-21_08-18-55
- 2026-09-20_08-22-25
- 2026-09-20_08-20-02
- 2026-09-19_08-21-04
- 2026-09-19_08-19-17
- 2026-09-18_08-25-28
- 2026-09-18_08-23-29
- 2026-09-17_08-19-52
- 2026-09-17_08-17-26
- 2026-09-16_08-17-02
- 2026-09-16_08-14-56
- 2026-09-15_08-18-43
- 2026-09-15_08-17-03
- 2026-09-14_08-18-37
- 2026-09-14_08-16-11
- 2026-09-13_08-18-40
- 2026-09-13_08-16-34
- 2026-09-12_08-21-49
- 2026-09-12_08-19-20
- 2026-09-11_08-20-31
- 2026-09-11_08-18-50
- 2026-09-10_08-19-31
- 2026-09-10_08-17-10
- 2026-09-09_08-19-52
- 2026-09-09_08-17-25
- 2026-09-08_08-18-40
- 2026-09-08_08-17-02
- 2026-09-07_08-15-44
- 2026-09-07_08-14-11
- 2026-09-06_08-16-54
- 2026-09-06_08-14-50
- 2026-09-05_08-16-30
- 2026-09-05_08-14-18
- 2026-09-04_08-14-17
- 2026-09-04_08-12-30
- 2026-09-03_08-14-27
- 2026-09-03_08-12-25
- 2026-09-02_08-15-48
- 2026-09-02_08-14-04
- 2026-09-01_08-14-24
- 2026-09-01_08-12-46
- 2026-08-31_08-17-17
- 2026-08-31_08-15-15
- 2026-08-30_08-10-18
- 2026-08-30_08-08-25
- 2026-08-29_08-11-57
- 2026-08-29_08-09-49
- 2026-08-28_08-14-31
- 2026-08-28_08-12-48
- 2026-08-27_08-06-02
- 2026-08-27_08-04-10
- 2026-08-25_08-11-50
- 2026-08-25_08-10-09
- 2026-08-24_08-06-18
- 2026-08-24_08-04-38
- 2026-08-23_08-05-27
- 2026-08-23_08-04-12
- 2026-08-22_08-06-16
- 2026-08-22_08-04-30
- 2026-08-21_08-01-15
- 2026-08-21_08-00-11
- 2026-08-20_08-05-00
- 2026-08-20_08-03-26
- 2026-08-19_08-04-05
- 2026-08-19_08-02-46
- 2026-08-18_08-00-42
- 2026-08-18_07-59-32
- 2026-08-17_08-00-19
- 2026-08-17_07-59-02
- 2026-08-16_07-56-52
- 2026-08-16_07-55-40
- 2026-08-15_07-58-22
- 2026-08-15_07-57-11
- 2026-08-14_07-58-07
- 2026-08-14_07-56-53
- 2026-08-13_07-57-58
- 2026-08-13_07-56-54
- 2026-08-12_07-56-29
- 2026-08-12_07-55-33
- 2026-08-11_07-57-30
- 2026-08-11_07-55-50
- 2026-08-10_07-53-46
- 2026-08-10_07-52-42
- 2026-08-09_07-53-27
- 2026-08-09_07-52-11
- 2026-08-08_07-52-58
- 2026-08-08_07-51-48
- 2026-08-07_07-51-16
- 2026-08-07_07-50-08
- 2026-08-06_07-52-17
- 2026-08-06_07-51-10
- 2026-08-05_07-54-02
- 2026-08-05_07-52-38
- 2026-08-04_07-53-39
- 2026-08-04_07-52-30
- 2026-08-02_07-51-55
- 2026-08-02_07-50-49
- 2026-08-01_07-51-44
- 2026-08-01_07-50-42
- 2026-07-31_07-50-14
- 2026-07-31_07-49-10
- 2026-07-30_07-49-39
- 2026-07-30_07-48-29
- 2026-07-29_07-50-47
- 2026-07-29_07-49-43
- 2026-07-28_07-50-29
- 2026-07-28_07-49-22
- 2026-07-27_07-46-18
- 2026-07-27_07-45-27
- 2026-07-26_07-44-40
- 2026-07-26_07-43-43
- 2026-07-25_07-45-08
- 2026-07-25_07-44-00
- 2026-07-24_07-45-24
- 2026-07-24_07-44-30
- 2026-07-23_07-44-30
- 2026-07-23_07-43-26
- 2026-07-22_07-46-11
- 2026-07-22_07-45-18
- 2026-07-21_07-43-25
- 2026-07-21_07-42-25
- 2026-07-18_07-43-43
- 2026-07-18_07-42-49
- 2026-07-16_07-29-21
- 2026-07-16_07-28-42
- 2026-07-14_07-27-51
- 2026-07-14_07-27-10
- 2026-07-12_07-28-48
- 2026-07-12_07-27-59
- 2026-07-11_07-27-56
- 2026-07-11_07-27-10
- 2026-07-10_07-27-31
- 2026-07-10_07-26-50
- 2026-07-09_07-27-28
- 2026-07-09_07-26-38
- 2026-07-08_07-27-24
- 2026-07-08_07-26-36
- 2026-07-06_07-27-11
- 2026-07-06_07-26-34
- 2026-07-05_07-24-39
- 2026-07-05_07-23-47
- 2026-07-04_07-25-55
- 2026-07-04_07-25-14
- 2026-07-03_07-25-30
- 2026-07-03_07-24-52
- 2026-07-02_07-24-41
- 2026-07-02_07-23-59
- 2026-07-01_07-38-15
- 2026-07-01_07-37-38
- 2026-06-30_09-49-01
- 2026-06-30_07-34-49
- 2026-06-29_11-34-51
- 2026-06-29_07-37-32
- 2026-06-28_09-31-45
- 2026-06-28_07-33-59
- 2026-06-27_09-32-17
- 2026-06-27_07-34-34
- 2026-06-27_07-34-06
- 2026-02-18_06-57-14
- 2024-11-23_03-30-32
- 2024-09-30_21-22-35
- 2024-07-04_15-01-35
- 2024-03-30_14-17-45
Check the differences between the versions.
Annotations
Events
Hand-picked events relevant to this call topic.
No events yet
There are currently no events linked to this call topic.
Timeline
Call published · 30 Sep 2024 (2 years ago)
All expected milestones for this call have passed.
Work programme published
07 Oct 2022 · est.
Call opens
12 Sep 2023
Call closes
16 Jan 2024
Outcome expected
16 Jun 2024 · est.
Grant agreement signed
16 Sep 2024 · est.
Call published
30 Sep 2024
-
Work programme published Estimated
07 Oct 2022 · 4 years ago
Topics are listed in the Work Programme before the call opens. Spotting this early gives you a head start on partner search and proposal planning.
-
Call opens
12 Sep 2023 · 3 years ago
Submissions can be made from this date.
-
Call closes
16 Jan 2024 · 2 years ago
Deadline to submit a proposal.
-
Outcome expected Estimated
16 Jun 2024 · 2 years ago
The maximum time to inform applicants of the evaluation outcome is five months after the call closes.
-
Grant agreement signed Estimated
16 Sep 2024 · 2 years ago
The maximum time to sign the grant agreement is three months after applicants are informed of the outcome.
-
Call published
30 Sep 2024 · 2 years ago
This topic was first published in TopicTree.
Funded Projects
Loading...
Project information comes from CORDIS (for Horizon 2020 and Horizon Europe) and will be sourced from F&T Portal (for Digital Europe projects)
Ecosystem bubbles
This call topic is part of the following thematic bubbles.
Not part of a bubble yet
This call topic has not been grouped into an ecosystem bubble.